Monthly Archives: August 2016
Bremer Bay -More Fine Tuning
More of the Same Monday 15 August Nino and Ash were back at it again this week. Another brief respite in the terrible weather gave them a window to apply the roof flashing. However, as usual, it is not the normal cut for the … Continue reading
Bremer Bay – Plumbing & A Short Week
Things That need to be done, get done. Monday 8th August: No builders onsite today as both took the time to attend to other matters. Ash having worked nearly non-stop for the past 10 weeks, and of course Nino is only back home … Continue reading
Bremer Bay – The Roof is Upon Us
Preamble: In the times between waiting for the box gutter to be manufactured, and the roof iron to be cut and delivered, the last few weeks have been spent fine tuning, straightening, bracing, aligning, forming around the protruding steel and inserting trimmers in the internal … Continue reading